(855) 474-5464

moc.elipasrev%40selas

327ft Guyed Tower Converted From Concrete Foundation to Helical Piles

Saves client big on time, budget, and raw materials

Client

Bell MTS

Project

327ft Guyed Communication Tower

Pile Details

● 219mm [8-5/8"] Ø shaft, 8.2mm [0.322"] thick wall, 660mm [26"] double helix at 25mm [1"] thickness● 219mm [8-5/8"] Ø shaft, 13mm [0.5"] thick wall, 660mm [26"] double helix at 32mm [1-1/4"] thickness

Foundation Loads

● 14kN [3.1kips] Shear ● 1,846.6kN [415kips] Axial

Anchor Loads

● 563.3kN [126.6kips] Uplift● 609.4kN [137kips] Axial

Certified welder performing fabrication work on helical pile foundation
Illustration of bulky concrete foundation originally specified for tower. Large block of concrete buried in ground with guy wire support embedded in concrete
Illustration of large diameter poured concrete pile installed into ground

Problem

VersaPile was engaged prior to construction by Bell MTS to support a 99.8m [327ft] communications guyed tower to bring 5G cellular voice and data service to the surrounding community of Lac Du Bonnet, Manitoba.
The geotechnical investigation conducted by Wood encountered auger refusal at 11.4m [37'-6"ft] depth in till consisting of N values in excess of 30 with sloughing and seepage observed from 2.6m to 3.1m as well as 10.4m to 10.7m.
The original foundation solution was a concrete foundation consisting of a 6ft x 38ft caisson for the centre tower and three massive deadman anchor blocks with 26ft anchor channels.
The project was to be completed in the summer of 2022 following record breaking levels of precipitation in the area. This meant that the site, which already experienced sloughing and seepage, was very saturated.
To complete the project with concrete meant additional site preparation, rig matting as well as major de-watering efforts. In addition to these potentially significant price escalations, concrete foundation contractors in the area were behind in scheduling due to the consistent rain and already saturated soils in the area.
Bell MTS, who had never built a 100m (327ft) guyed tower on anything but a concrete foundation, brought the project to VersaPile Inc. to consider helical piles.

Solution

VersaPile engaged Cory Goulet P.Eng. of Pilisk Geostructural to analyze soils and tower design to engineer an alternative foundation solution using helical piles.

The solution was to replace the large concrete caisson under the tower with a 4 pile grouping of helical piles installed on opposing 10 degree batters. The massive concrete deadmen anchors were replaced each with a single helical pile installed on a 42.8 degree batter.

VersaPile, with a team of project engineers, installed 7 helical piles with pile caps site welded by Reg Dumont of DC Custom Welding. The project was completed successfully despite the challenging marsh like conditions.
The centre piles were installed using VersaPile's CASE CX350 with a Digga UD300 anchor drive. More difficult guy-anchor locations were accessed by the lighter John Deere 290G with an Eskridge D1400 anchor drive.

Illustration of helical pile installed to glacial till, pile is installed at angle
Illustration of one vertical helical pile and a battered helical  pile providing support to vertical helical pile
Large excavator installing helical pile in rough terrain

Conclusion

Bell MTS was very satisfied with the results and would no longer be reluctant to construct tall guyed towers on helical piles.
They realized savings in excess of $225,000 to the budget and avoided many potential cost escalations related to digging, drilling and working in sloughing and seeping soils.
The timeline for the project was also reduced by at least 2 weeks (and likely longer) as water would have surely slowed down typical production times.
There was also a huge savings in raw materials on the project.
Original concrete designs called for 448 tonnes of reinforced concrete material. Our helical pile solution, in comparison, required a mere 6 tonnes of steel material for the foundation.
That means helical piles used 98.6% less raw material than concrete, an enormous reduction that greatly reduced land impact. The result was a faster, easier, cleaner support for this impressive communication tower.

Contact Us

Address

2046 Van Gorp Road
Ile Des Chenes, MB
Canada R0A 0T0

Hours

Monday - Friday8:00 - 17:00

Contact

(234) 567-8900moc.elipasrev%40olleh

Thank you!

We will contact you shortly

Can't send form.

Please try again later.