(855) 474-5464

moc.elipasrev%40selas

Complete Helical Pile Foundation for Custom Luxury Home Near The Red River

When a custom home builder ran into saturated and sloughing soils on the intended site of a luxury home, it would take a helical pile solution to save the day

Client

Maric Homes

Project

Custom Luxury Home

Pile Details

● 37 - 4-1/2" dia., 40'-50' long shaft, 16" dia. helical● 185 kip (814 kN) ULS, req. torque: 115 kip-ft (155 kN-m)

Capacity

40 kip [178 kN] ULS, f.

Key Challenges

● Saturated & Sloughing Soils● Low Bearing Capacity● Winter Construction

Custom luxury home with landscaping on side of house
Side view of large excavator installing helical pile in snow

Problem

VersaPile was engaged to provide an end bearing alternative to concrete friction piles due to low capacity, highly saturated and sloughing soils.
Due to these soil challenges, this custom home project was at risk of suffering significant delays. Alternative end bearing piles such as precast concrete or timber driven piles were considered, however they came with both a significant increase in cost and the potential to cause extensive delays.
Additionally, the depth to till was variable and difficult to predict on this site. It was clear that a different deep foundation was required in order to get this project back on-track and on-budget.

Solution

Maric Homes engaged VersaPile to design and have engineered thirty-seven helical piles, suitable for 40 kips of load, to support the home.
Our team anticipated, based on the soils data provided, that from excavated depth till would be encountered at approximately 36 - 37 feet. Accordingly, our team brought 40 feet of pile to the site.
In reality, while some piles did refuse prior to 40 feet, many had be extended an additional 10 feet in order to hit refusal up to 50 feet deep.
To extended some of the helical piles further, VersaPile quickly secured pipe to match the helical pile shafts. Our crew worked over the weekend to weld the extensions on the helical piles and continue turning them into the ground. Once the piles reached refusal, the extension was cut from the pile and used to extend the next pile. This ensured maximum efficiency of additional materials and minimized waste.
Because of this fix, additional costs to install piles deeper than predicted was kept to a minimum. Timelines were only impacted by one single day, as our crews worked over the weekend to lengthen piles as necessary.
Mobilizing in winter with a CAT 321D excavator, equipped with Pengo RT20 anchor drive, VersaPile's crew was able to penetrate frost without pre-drilling and successfully install all piles to till.
Had precast or timber driven piles been selected by the customer, they would have had to abandon piles which failed to refuse, making them unusable, and come back with longer piles. The till varied greatly from pile to pile which would have made it difficult for piling contractors installing timber or precast piles to predict. The cost increase from such situations tends to be exponential, as larger pile rigs are mobilized to install longer piles. Timelines are also at risk, with these delays often adding weeks to the foundation installation.

Side view of large excavator installing helical pile in snow
Front view of luxury home with landscaping in front
Custom luxury home with landscaping on side of house

Conclusion

VeraPile was able to help Maric Homes find a cost-effective and timely solution for their unforseen soils issues.
Thirty-seven (37) high-capacity helical piles were installed to support the luxury custom built home. Maric Homes was pleased with the results and appreciated the fact that while increased costs and timelines are not fun, helical piles were indispensable in keeping impacts to a minimum.

Contact Us

Address

2046 Van Gorp Road
Ile Des Chenes, MB
Canada R0A 0T0

Hours

Monday - Friday8:00 - 17:00

Contact

(234) 567-8900moc.elipasrev%40olleh

Thank you!

We will contact you shortly

Can't send form.

Please try again later.